Flood Control and Drainage17IF0016

CONSTRUCTION/ MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE - CONSTRUCTION OF BACAN FLOOD CONTROL, BRGY. TINAG-AN, ALBUERA, LEYTE, 4TH LD

CONSTRUCTION/ MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE - CONSTRUCTION OF BACAN FLOOD CONTROL, BRGY. TINAG-AN, ALBUERA, LEYTE, 4TH LD is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱19,381,046.98. Status: Reported complete (DPWH). Contractor on record: OCTAGON CONCRETE SOLUTIONS INC. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bacan Flood Control, Brgy. Tinag-an, Albuera, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-17-0021054

₱487,933.00 · FY2017

Released to 'Amang' Rodriguez Re Medical Center fo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

69 projects · ₱6.7B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM (LP) - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF TACLOBAN AIRPORT PASSENGER TERMINAL BUILDING PHASE 3, TACLOBAN CITY

Region VIII, Region VIII

2024₱964.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONST. OF AIRPORT FACILITY, BUSUANGA AIRPORT, CORON, PALAWAN

Region IV-B, Region IV-B

2024₱400.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS./S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF R0AD, BRGY. LIYANG, PILAR TO BRGY. BILOLO, ORION, BATAAN (PACKAGE 1)

Region III, Region III

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE K0115+949 TO K0118+000, ROXAS, PALAWAN

Region IV-B, Region IV-B

2018₱162.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM LEFTSIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱154.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM RIGHTIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱147.1M
Past target date (DPWH On-Going)
View all 69 projects →

4. Implementation

Contract Amount

₱19,381,046.98

Progress

Reported complete (DPWH)

Start Date

February 17, 2017

Target End

July 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.