Roads19DB0123

CONCRETING OF ROAD, BRGY. TALAGA, LEMERY, BATANGAS

CONCRETING OF ROAD, BRGY. TALAGA, LEMERY, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱9,504,854.92. Status: Reported complete (DPWH). Contractor on record: TOPTECH TRADING AND CONST CO INC. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Released to Bata National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

59 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BARANGAY POBLACION 4 -

Batangas 2nd DEO, Region IV-A

2025₱140.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS - DIOKNO HIGHWAY - K0079 + 000 - K0080 + 600

Batangas 1st DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-SECONDARY ROADS ALONG TAGAYTAY-NASUGBU RD - K0087+719-K0090+000

Batangas 1st DEO, Region IV-A

2018₱95.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING SECONDARY ROADS, NASUGBU-LIAN-CALATAGAN RD - K0100+500 - K0101+244, K0101+268 - K0102+000, LIAN, BATANGAS

Batangas 1st DEO, Region IV-A

2020₱94.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - PALICO-BALAYAN-BATANGAS RD - K0098 + 810 - K0099 + 064, K0100 + 000 - K0100 + 553

Batangas 1st DEO, Region IV-A

2023₱78.9M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS, NASUGBU-LIAN-CALATAGAN ROAD - K0107+209 - K0108+000, K0114+890 - K0116+846, K0120+066 - K0121+000, K0123+000 - K0124+746

Batangas 1st DEO, Region IV-A

2019₱77.2M
Reported complete (DPWH)
View all 59 projects →

4. Implementation

Contract Amount

₱9,504,854.92

Progress

Reported complete (DPWH)

Start Date

August 14, 2019

Target End

December 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.