Water Provision and Storage19PK0058

CONSTRUCTION OF WATERWORK OF BRGY. SUMADEL I AND SUMADEL II, TINGLAYAN, KALINGA

CONSTRUCTION OF WATERWORK OF BRGY. SUMADEL I AND SUMADEL II, TINGLAYAN, KALINGA is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱988,384.48. Status: Reported complete (DPWH). Contractor on record: CHONG CONST AND SUPPLIES. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-19-0008731

₱92,803.00 · FY2019

Released to Balugo National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

26 projects · ₱86.3M total · 0 flags

4. Implementation

Contract Amount

₱988,384.48

Progress

Reported complete (DPWH)

Start Date

July 10, 2019

Target End

August 30, 2019

5. Audit