Buildings and Facilities21GP0075

CONSTRUCTION/COMPLETION OF 4STY12CL, SAPIAN NATIONAL HIGH SCHOOL, SAPI-AN, CAPIZ

CONSTRUCTION/COMPLETION OF 4STY12CL, SAPIAN NATIONAL HIGH SCHOOL, SAPI-AN, CAPIZ is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱3,197,325.30. Status: Reported complete (DPWH). Contractor on record: 7 JL HARDWARE. Figures trace to dpwh.

Capiz 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,400,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Sitio SWA, Brgy. Poblacion, President Roxas, Capiz City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Capiz 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,197,325.30

Progress

Reported complete (DPWH)

Start Date

November 10, 2021

Target End

January 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.