GAA 2025 OO-225AG0029

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ALAMINOS RIVER, AMANDIEGO SECTION, BARANGAY AMANDIEGO, ALAMINOS CITY,PANG

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ALAMINOS RIVER, AMANDIEGO SECTION, BARANGAY AMANDIEGO, ALAMINOS CITY,PANG is a DPWH-tracked public work in Pangasinan 1st DEO, Region I. Reported contract value: ₱95,519,801.25. Status: Reported complete (DPWH). Contractor on record: CDC CONST. Figures trace to dpwh.

Pangasinan 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structures, Barangay Siapar, Anda, Pangasinan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Pangasinan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

88 projects · ₱2.6B total · 0 flags

4. Implementation

Contract Amount

₱95,519,801.25

Progress

Reported complete (DPWH)

Start Date

March 26, 2025

Target End

November 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.