Roads21PF0050

IMPROVEMENT OF AURORA STREET TO GATE 1 LEPANTO MUNICIPAL ROAD, BARANGAY POBLACION, MANKAYAN, BENGUET, STA. 0+300 STA. 0+637

IMPROVEMENT OF AURORA STREET TO GATE 1 LEPANTO MUNICIPAL ROAD, BARANGAY POBLACION, MANKAYAN, BENGUET, STA. 0+300 STA. 0+637 is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: SHARAMALLE CONST AND GEN ENGINEERING. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Taneg Flood Control Sta. 13+991 - Sta. 14+711 (R.S.), Mankayan, Benguet
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Benguet 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱105.7M total · 0 flags

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

January 10, 2022

Target End

May 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.