Construction of Revetment22KB0074

Construction of Revetment, Downstream and Upstream of Musuan Bridge along Taganibong Creek, Maramag, Bukidnon

Construction of Revetment, Downstream and Upstream of Musuan Bridge along Taganibong Creek, Maramag, Bukidnon is a DPWH-tracked public work in MARAMAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱23,520,000.00. Status: Reported complete (DPWH). Contractor on record: PHILIPPIANS CDO CONST CORP. Figures trace to sumbong.

MARAMAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sagayaran Bridge including approaches and flood control, Kinura, Kalilangan, Bukidnon (Phase 1)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003123

₱718,520,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0010240

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005381

₱5,751,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003061

₱3,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005382

₱572,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

22 projects · ₱274.6M total · 0 flags

4. Implementation

Contract Amount

₱23,520,000.00

Progress

Reported complete (DPWH)

Start Date

February 10, 2022

Target End

November 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.