Construction of Flood Mitigation Structure21OD0189

Construction/Rehabilitation of Flood Control Wall along Bank of Creeks in Barangay 178, 185, 186, 187, 188, Caloocan City

Construction/Rehabilitation of Flood Control Wall along Bank of Creeks in Barangay 178, 185, 186, 187, 188, Caloocan City is a DPWH-tracked public work in CALOOCAN CITY, National Capital Region. Reported contract value: ₱28,663,271.48. Status: Reported complete (DPWH). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST. Figures trace to sumbong.

CALOOCAN CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Wall along Bank of Creeks in Barangay 178, 185, 186, 187, 188, Caloocan City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010297

₱99,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014192

₱58,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010199

₱140,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010191

₱17,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013890

₱5,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013868

₱57,000,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

170 projects · ₱10.0B total · 10 flags

4. Implementation

Contract Amount

₱28,663,271.48

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

November 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.