Flood Control and Drainage18EI0054

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CAVILLIAN RIVER CONTROL STRUCTURES, BULALACAO, ORIENTAL MINDORO

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CAVILLIAN RIVER CONTROL STRUCTURES, BULALACAO, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱28,215,017.38. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cavillan River Control Structure, Bulalacao, Oriental Mindoro
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

299 projects · ₱22.3B total · 0 flags

4. Implementation

Contract Amount

₱28,215,017.38

Progress

Reported complete (DPWH)

Start Date

April 24, 2018

Target End

January 15, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.