GAA 2020 OO-120EI0110

ROAD WIDENING - SECONDARY ROADS BONGABONG - SAGANA - ROXAS - SAN AQUILINO ROAD - K0114+268.20 - K0115+635.00, BONGABONG, ORIENTAL MINDORO

ROAD WIDENING - SECONDARY ROADS BONGABONG - SAGANA - ROXAS - SAN AQUILINO ROAD - K0114+268.20 - K0115+635.00, BONGABONG, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱32,556,072.94. Status: Past target date (DPWH On-Going). Contractor on record: ALBERTO UY CONST. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱28,608,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Bongabong River, Mapang Section, Bongabong, Oriental Mindoro
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Southern Mindoro DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱32,556,072.94

Progress

Past target date (DPWH On-Going)

Start Date

December 11, 2020

Target End

December 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.