GAA 2025 DA FMR25IF0087

CONCRETING OF BRGY. CATIGAHAN TO BRGY. SAN PABLO TO BRGY. SAN ROQUE FMR (PHASE II), BRGYS. CATIGAHAN, SAN PABLO AND SAN ROQUE, PALOMPON, LEYTE

CONCRETING OF BRGY. CATIGAHAN TO BRGY. SAN PABLO TO BRGY. SAN ROQUE FMR (PHASE II), BRGYS. CATIGAHAN, SAN PABLO AND SAN ROQUE, PALOMPON, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱23,879,999.75. Status: Past target date (DPWH On-Going). Contractor on record: CIRCLE Z VENTURES. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tugbong CIS, Kananga, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

242 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱23,879,999.75

Progress

Past target date (DPWH On-Going)

Start Date

June 18, 2025

Target End

December 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.