Flood Control and Drainage24K00378

CONSTRUCTION OF GATA RIVER FLOOD CONTROL WITH SLOPE PROTECTION, BRGY. CAIRAN, ROGAN, POONA BAYABAO, LANAO DEL SUR

CONSTRUCTION OF GATA RIVER FLOOD CONTROL WITH SLOPE PROTECTION, BRGY. CAIRAN, ROGAN, POONA BAYABAO, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱32,479,506.40. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M M A ACHIEVER CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱32,479,506.40

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 30, 2024

Target End

May 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.