Water Provision and Storage20FO0055

CONSTRUCTION OF WATER SYSTEM LEVEL 2, SAN ISIDRO, SAN ROQUE, AND SALVACION, JOVELLAR, ALBAY

CONSTRUCTION OF WATER SYSTEM LEVEL 2, SAN ISIDRO, SAN ROQUE, AND SALVACION, JOVELLAR, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱2,819,841.30. Status: Reported complete (DPWH). Contractor on record: PLASWEALTH PHILS CORP. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Franciso River Flood Control Structure, Guinobatan, Albay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,819,841.30

Progress

Reported complete (DPWH)

Start Date

February 24, 2020

Target End

July 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.