Construction of Dike22FB0005

Construction of Cagsawa Ruins Protection Dike (Tributary ''F''), Daraga, Albay

Construction of Cagsawa Ruins Protection Dike (Tributary ''F''), Daraga, Albay is a DPWH-tracked public work in DARAGA (LOCSIN) (ALBAY), ALBAY, Region V. Reported contract value: ₱67,547,845.61. Status: Reported complete (DPWH). Contractor on record: NUMERICAL GATE CONST & SUPPLY CORP. Figures trace to sumbong.

DARAGA (LOCSIN) (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Muladbucad Flood Control Dike in Muladbucad, Guinobatan, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001737

₱187,700,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002950

₱120,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001730

₱80,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001631

₱60,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002890

₱2,150,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002436

₱47,688,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001623

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001966

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001965

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003024

₱50,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

9 projects · ₱678.2M total · 0 flags

Other projects by this contractor

View all 9 projects →

4. Implementation

Contract Amount

₱67,547,845.61

Progress

Reported complete (DPWH)

Start Date

March 4, 2022

Target End

October 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.