Roads24FO0085

CONCRETING OF BRGY. ESTRELLA, JOVELLAR TO BGRY. RAWIS, PIO DURAN FMR, BRGY. ESTRELLA, JOVELLAR AND BRGY. RAWIS, PIO DURAN, ALBAY

CONCRETING OF BRGY. ESTRELLA, JOVELLAR TO BGRY. RAWIS, PIO DURAN FMR, BRGY. ESTRELLA, JOVELLAR AND BRGY. RAWIS, PIO DURAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱13,897,711.55. Status: Past target date (DPWH On-Going). Contractor on record: EC SAGPON CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,897,711.55

Progress

Past target date (DPWH On-Going)

Start Date

July 15, 2024

Target End

December 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.