CONSTRUCTION OF ROAD AND DRAINAGE ALONG Q. DENIEGA STREET, E. GABRIEL STREET AND SANCHEZ STREET, BARANGAY ARKONG BATO, VALENZUELA CITY

CONSTRUCTION OF ROAD AND DRAINAGE ALONG Q. DENIEGA STREET, E. GABRIEL STREET AND SANCHEZ STREET, BARANGAY ARKONG BATO, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱24,324,259.10. Status: Reported complete (DPWH). Contractor on record: DSA PRIME BUILDERS CORP. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Nanay Nanayan Creek, Barangay 176, Caloocan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

24 projects · ₱417.5M total · 0 flags

4. Implementation

Contract Amount

₱24,324,259.10

Progress

Reported complete (DPWH)

Start Date

March 17, 2025

Target End

August 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.