Construction of Flood Mitigation Structure23IC0114

Construction of Flood Control along Binahaan River, Barangay Sta. Elena, Tanauan, Leyte

Construction of Flood Control along Binahaan River, Barangay Sta. Elena, Tanauan, Leyte is a DPWH-tracked public work in TANAUAN (LEYTE), LEYTE, Region VIII. Reported contract value: ₱106,099,996.40. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC / MWJ CONST. Figures trace to sumbong.

TANAUAN (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Binahaan River, Brgy. Baras, Tanauan, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱106,099,996.40

Progress

Reported complete (DPWH)

Start Date

June 29, 2023

Target End

May 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.