Buildings and Facilities25LF0070

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT) PUROK LOWER MANSANAS, BARANGAY SANTIAGO, CARAGA, DAVAO ORIENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT) PUROK LOWER MANSANAS, BARANGAY SANTIAGO, CARAGA, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 1st DEO, Region XI. Reported contract value: ₱7,839,452.15. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ECBJ EASTCOAST CONST. Figures trace to dpwh.

Davao Oriental 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Boston River San Jose Section, Boston, Davao Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Davao Oriental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,839,452.15

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 8, 2025

Target End

August 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.