Flood Control and Drainage25CD0144

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG STO. CRISTO RIVER, STA. 10+450 STA.10+600, CITY OF SAN JOSE DEL MONTE, BULACAN

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG STO. CRISTO RIVER, STA. 10+450 STA.10+600, CITY OF SAN JOSE DEL MONTE, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱93,599,130.14. Status: Past target date (DPWH On-Going). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Angat River, Poblacion Section, Sta.14+834 - Sta. 14+922, Norzagaray, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

328 projects · ₱20.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF PAMPANGA

Region III, Region III

2023₱228.7M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, MANGATAREM-STA CRUZ ROAD, PACKAGE 2, PANGASINAN

Region I, Region I

2018₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS AND DECLARED TOURISM DESTINATIONS, CONCRETING OF ROAD FROM LINGAYEN BAYWALK TO BINMALEY, PANGASINAN

Region I, Region I

2016₱185.6M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 2, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 3, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
View all 328 projects →

4. Implementation

Contract Amount

₱93,599,130.14

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

January 20, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.