Flood Control and Drainage24CG0329

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱140,418,459.00. Status: Past target date (DPWH On-Going). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱35,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱140,418,459 · ROYAL CROWN MONARCH CONST & SUPPLIES CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    90% reported · imagery 2021-10-29 → 2025-11-21

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Pampanga

Based on the coordinates published with the DPWH record and NOAH file Pampanga.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cabalantian Creek ( Phase II ) , Bacolor, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Pampanga 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24CG0329 - Flood Management Program Construction/

₱140,418,459.00 · ROYAL CROWN MONARCH CONST & SUPPLIES CORP

Award / contract ref: 24CG0329

Contractor

A

328 projects · ₱20.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF PAMPANGA

Region III, Region III

2023₱228.7M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, MANGATAREM-STA CRUZ ROAD, PACKAGE 2, PANGASINAN

Region I, Region I

2018₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS AND DECLARED TOURISM DESTINATIONS, CONCRETING OF ROAD FROM LINGAYEN BAYWALK TO BINMALEY, PANGASINAN

Region I, Region I

2016₱185.6M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 2, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 3, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD ALONG SETBACK LEVEE, PHASE II, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱140.4M
Past target date (DPWH On-Going)
View all 328 projects →

4. Implementation

Contract Amount

₱140,418,459.00

Progress

Past target date (DPWH On-Going)

Start Date

January 13, 2025

Target End

December 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.