Water Provision and Storage21DL0173

CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM RAINWATER COLLECTOR SYSTEMA. DOÑA MARTA HOSPITAL, ATIMONAN, QUEZONB. SOUTHERN LUZON STATE UNIVERSITY (SLSU) CALA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM RAINWATER COLLECTOR SYSTEMA. DOÑA MARTA HOSPITAL, ATIMONAN, QUEZONB. SOUTHERN LUZON STATE UNIVERSITY (SLSU) CALA is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱4,373,323.08. Status: Reported complete (DPWH). Contractor on record: MURIELEVEN BUILDERS AND CONST SUPPLY CORP. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/ Rehabilitation of Flood Control Structures along Boong River, Brgys. Villa Victoria and Bacong, Alabat, Quezon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Quezon 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

192 projects · ₱1.6B total · 5 flags

Other projects by this contractor

View all 192 projects →

4. Implementation

Contract Amount

₱4,373,323.08

Progress

Reported complete (DPWH)

Start Date

October 10, 2022

Target End

February 6, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.