Flood Control and Drainage18CK0034

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG LUCUNG RIVER (CUT-CUT 1 SECTION, LEFT BANK), UPSTREAM OF CUT-CUT BRIDGE, CAPAS, TARLAC

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG LUCUNG RIVER (CUT-CUT 1 SECTION, LEFT BANK), UPSTREAM OF CUT-CUT BRIDGE, CAPAS, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱23,270,600.96. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Existing Dike along Lucung River (Cut-Cut 1st Section, Left Bank), U/S of Cut-Cut Bridge, Capas, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0029562

₱0.00 · FY2018

Released to Division of Tarlac (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

145 projects · ₱5.8B total · 2 flags

4. Implementation

Contract Amount

₱23,270,600.96

Progress

Reported complete (DPWH)

Start Date

February 1, 2018

Target End

June 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.