Flood Control and Drainage25NH0091

CONSTRUCTION / IMPROVEMENT OF BONGTUD FLOOD CONTROL STRUCTURE, TANDAG CITY SURIGAO DEL SUR

CONSTRUCTION / IMPROVEMENT OF BONGTUD FLOOD CONTROL STRUCTURE, TANDAG CITY SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 1st DEO, Region XIII. Reported contract value: ₱48,838,389.74. Status: Past target date (DPWH On-Going). Contractor on record: ARQ BUILDERS. Figures trace to dpwh.

Surigao del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Bongtud Flood Control Structure, Tandag City Surigao Del Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Surigao del Sur 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Probable match · 95%

Construction Projects

₱51,174,747.90 · ARQ BUILDERS

Contractor

B

206 projects · ₱12.5B total · 1 flags

4. Implementation

Contract Amount

₱48,838,389.74

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

March 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.