Roads19DL0053

C. CONVERGENCE AND SPECIAL SUPPORT PROGRAM 1. CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS 20. ACCESS ROAD LEADING TO PRISTINE BEACHES, TAGKAWAYAN, QUEZON

C. CONVERGENCE AND SPECIAL SUPPORT PROGRAM 1. CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS 20. ACCESS ROAD LEADING TO PRISTINE BEACHES, TAGKAWAYAN, QUEZON is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱7,642,052.19. Status: Reported complete (DPWH). Contractor on record: BOMEL CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-19-0004171

₱46,809,683.00 · FY2019

Released to Jose R. Reyes Memorial Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

77 projects · ₱1.4B total · 2 flags

Other projects by this contractor

No sat.

(SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF GUINAYANGAN - TAGKAWAYAN ROAD (SAN ROQUE - SEGUIWAN - KATIMO - KINATAKUTAN SECTION), TAGKAWAYAN, QUEZON

Quezon 4th DEO, Region IV-A

2024₱112.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, 17. CONSTRUCTION/ IMPROVEMENT OF ACCESS R

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 15. REHABILITATION OF SUMULONG-GUINAYANGAN ROAD, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PIRIS RIVER, BUENAVISTA, PACKAGE 1, QUEZON, BUENAVISTA, QUEZON

Quezon 3rd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 6. GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, QUEZON

Quezon 4th DEO, Region IV-A

2022₱66.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - PRIMARY ROADS 2. QUIRINO H-WAY - K0264 + 406 - K0265 + 140

Quezon 4th DEO, Region IV-A

2024₱47.5M
Reported complete (DPWH)
View all 77 projects →

4. Implementation

Contract Amount

₱7,642,052.19

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

August 24, 2019