Flood Control and Drainage24K00357

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, KOLAMBUGAN, LANAO DEL NORTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, KOLAMBUGAN, LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱88,925,322.74. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ARCINUE COMM'L CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

118 projects · ₱5.4B total · 3 flags

4. Implementation

Contract Amount

₱88,925,322.74

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

September 26, 2024

Target End

September 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.