Bridges19MH0016

WIDENING OF PERMANENT BRIDGES - KAWA BRIDGE 2 (B01541MN) ALONG SEN. NINOY AQUINO-LEBAK-KALAMANSIG ROAD SEN. NINOY AQUINO, SULTAN KUDARAT

WIDENING OF PERMANENT BRIDGES - KAWA BRIDGE 2 (B01541MN) ALONG SEN. NINOY AQUINO-LEBAK-KALAMANSIG ROAD SEN. NINOY AQUINO, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱19,024,178.60. Status: Reported complete (DPWH). Contractor on record: WOODRIDGE BUILDERS CONST. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0021904

₱9,500,000.00 · FY2019

Released to Units (AFPWS (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

66 projects · ₱1.2B total · 0 flags

Other projects by this contractor

View all 66 projects →

4. Implementation

Contract Amount

₱19,024,178.60

Progress

Reported complete (DPWH)

Start Date

June 19, 2019

Target End

December 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.