Buildings and Facilities22CD0098

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAPANG TALON, BRGY. NAGBALON, MARILAO, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAPANG TALON, BRGY. NAGBALON, MARILAO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱9,785,821.55. Status: Reported complete (DPWH). Contractor on record: 747 BUILDERS. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Strucrure (Slope Protection), Brgy. Lambakin, Marilao, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bulacan 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

125 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY STA.CLARA

Cavite 1st DEO, Region IV-A

2023₱28.9M
Reported complete (DPWH)
No sat.

CONCRETING OF BARANGAY PARADISE III FMR, BARANGAY PARADISE III, SAN JOSE DEL MONTE CITY, BULACAN

Bulacan 2nd DEO, Region III

2023₱24.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSASPHALT OVERLAY, ARNALDO HIGHWAY, BARANGAY SAN FRANCISCO, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2021₱24.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- TERTIARY ROADS-2ND STREET (FROM BONIFACIO DRIVE TO BASECO AREA)

South Manila DEO, National Capital Region

2024₱24.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1, ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS, KAWIT-NOVELETA DIVERSION RD. - K0022+(-364) - K0022+(-299), K0022+(-224) - K0022+(-167), K0022+(-167) - K0022+(-106), K0022

Cavite 1st DEO, Region IV-A

2020₱23.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL BRIDGES - CONSTRUCTION OF GREGORIO LUNA BRIDGE AT LIGTONG 4, ROSARIO, CAVITE

Cavite 1st DEO, Region IV-A

2019₱22.8M
Reported complete (DPWH)
View all 125 projects →

4. Implementation

Contract Amount

₱9,785,821.55

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

December 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.