Buildings and Facilities16CI0037

CONST OF FOUR(4) STOREY 16 CLASSROOMS ANGELES CITY NATL TRADE SCHOOL, ANGELES CITY, PAMP

CONST OF FOUR(4) STOREY 16 CLASSROOMS ANGELES CITY NATL TRADE SCHOOL, ANGELES CITY, PAMP is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱22,427,827.89. Status: Reported complete (DPWH). Contractor on record: AL-B DEVELOPMENT CORP 11740. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 11740

57 projects · ₱1.3B total · 0 flags

Other projects by this contractor

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ABACAN RIVER, BARANGAY SAPALIBUTAD, ANGELES CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱96.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOF MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN ANGELES CITY, PAMPANGA (PHASE I)

Pampanga 3rd DEO, Region III

2024₱62.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL PROGRAM; CONST/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES;ANGELES CITY TOLL EXIT CONNECTING NLEX AND SCTEX IN SUPPORT OF HANDICRAFT, FURNITURE,MANUFACTURING,HOTEL, IT-IBPM GARMENTS AND TEXTILES IND

Pampanga 3rd DEO, Region III

2020₱57.9M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM; ROAD WIDENING SECONDARY ROADS; FRIENDSHIP CIRCUMFERENTIAL ROAD (WEST CIRCUM ROAD) INCLUDING ROW K0082+282 - K0084+400, K0086+589 - K0086+595, K0087+781 - K0088+086, K0088+327 - K0088+460, K0089+187 - K0089+589, A.C., PAMP.

Pampanga 3rd DEO, Region III

2018₱54.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM;FLOOD CONTROL AND DRAINAGE;FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF SLOPE PROTECTION WORKS WITH CONCRETE PAVEMENT ALONG ABACAN RIVER STA. 2+300 TO STA 2+852, ANGELES CITY,PAMPANGA

Pampanga 3rd DEO, Region III

2020₱49.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM;FLOOD CONTROL AND DRAINAGE;FLOOD CONTROL STRUCTURES/FACILITIES;CONST OF REINFORCED CONCRETE SLOPE PROTECTION ALONG SAPANGBALEN CREEK,MABALACAT CITY,PAMPANGA

Pampanga 3rd DEO, Region III

2019₱49.0M
Reported complete (DPWH)
View all 57 projects →

4. Implementation

Contract Amount

₱22,427,827.89

Progress

Reported complete (DPWH)

Start Date

June 2, 2016

Target End

February 26, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.