Flood Control and Drainage24DI0002

CONSTRUCTION OF RIVER PROTECTION STRUCTURE AT CABUYAO RIVER, NEAR BIGAA BARANGAY HALL, CABUYAO CITY, LAGUNA

CONSTRUCTION OF RIVER PROTECTION STRUCTURE AT CABUYAO RIVER, NEAR BIGAA BARANGAY HALL, CABUYAO CITY, LAGUNA is a DPWH-tracked public work in Laguna 2nd DEO, Region IV-A. Reported contract value: ₱28,635,593.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AARCON BUILDERS. Figures trace to dpwh.

Laguna 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Structure Phase 3, ( Biñan - Sta. Rosa Boundary ) , Biñan Side, Biñan City, Laguna
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Laguna 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Probable match · 94%

Construction Project

₱27,850,456.26 · AARCON BUILDERS

Contractor

386 projects · ₱11.2B total · 0 flags

Other projects by this contractor

DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱187.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0021 + (-158) - K0021 + 000, K0021 + (-229) - K0021 + (-158), K0021 + 000 - K0025 + 163

National Capital Region, National Capital Region

2024₱160.5M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0015 + 985 - K0016 + 087, K0016 + 303 - K0016 + 651; MC DONALD JCT-AGUINALDO H-WAY - K0015 + 274 - K0015 + 690 AND MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K

Cavite 3rd DEO, Region IV-A

2025₱140.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438

Cavite 1st DEO, Region IV-A

2025₱103.9M
Reported complete (100% progress, DPWH status On-Going)

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF BACOOR FLOOD CONTROL PROJECT INCL. A PUMPING STATION, (PACKAGE A), BACOOR CITY, CAVITE

Region IV-A, Region IV-A

2019₱103.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ASPHALT OVERLAY OF TANAY-SAMPALOC RD - K0066+100 - K0068+000, K0069+000 - K0070+443, TANAY, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱98.0M
Reported complete (DPWH)
View all 386 projects →

4. Implementation

Contract Amount

₱28,635,593.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 12, 2024

Target End

August 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.