Construction of Flood Mitigation Structure24A00265

Construction of River Control at Barangay Poblacion Norte, Poblacion Este, and Saoat, Sta. Cruz, Ilocos Sur

Construction of River Control at Barangay Poblacion Norte, Poblacion Este, and Saoat, Sta. Cruz, Ilocos Sur is a DPWH-tracked public work in SANTA CRUZ (ILOCOS SUR), ILOCOS SUR, Region I. Reported contract value: ₱29,853,362.81. Status: Reported complete (DPWH). Contractor on record: NORTH TECH BUILDERS AND CONST SUPPLY. Figures trace to sumbong.

SANTA CRUZ (ILOCOS SUR), ILOCOS SUR, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Busiing Norte, San Ildefonso, Ilocos Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007423

₱1,864,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007425

₱172,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0018197

₱153,535.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,853,362.81

Progress

Reported complete (DPWH)

Start Date

April 8, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.