GAA 2017 MFO-117NF0006

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REPLACEMENT OF PERMANENT WEAK BRIDGE, SECONDARY COMPLETION OF DAYWAN BRIDGE (B00987MN) W/ DETOUR (PHASE II), CLAVER, SURIGAO DEL NORTE, K1175+670.00 - K1175+850.00

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REPLACEMENT OF PERMANENT WEAK BRIDGE, SECONDARY COMPLETION OF DAYWAN BRIDGE (B00987MN) W/ DETOUR (PHASE II), CLAVER, SURIGAO DEL NORTE, K1175+670.00 - K1175+850.00 is a DPWH-tracked public work in Surigao del Norte 2nd DEO, Region XIII. Reported contract value: ₱59,074,096.36. Status: Reported complete (DPWH). Contractor on record: A T DUMLAO CONST INC FORMERLYANDONI T D. Figures trace to dpwh.

Surigao del Norte 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage System, Mayag Flood Control, Surigao del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0020340

₱-36,567,734.00 · FY2017

Released to Camarines Sur 3rd Is District Engineering Office al (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱59,074,096.36

Progress

Reported complete (DPWH)

Start Date

March 30, 2017

Target End

August 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.