Bridges17PK0146

RESTORATION OF BRIDGE APPROACH AND BRIDGE ABUTMENT OF BONOG BRIDGE ALONG, MT. PROVINCE BDRY.-CALANAN-PINUKPUK-ABBUT ROAD, KO436+358 - KO436+379, POBLACION, TINGLAYAN, KALINGA

RESTORATION OF BRIDGE APPROACH AND BRIDGE ABUTMENT OF BONOG BRIDGE ALONG, MT. PROVINCE BDRY.-CALANAN-PINUKPUK-ABBUT ROAD, KO436+358 - KO436+379, POBLACION, TINGLAYAN, KALINGA is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱5,983,567.94. Status: Reported complete (DPWH). Contractor on record: LUMINGAY DEVELOPMENT CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004567

₱528,000.00 · FY2016

Released to Hinabangan National High School (Rawis NHS) PS req (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

8 projects · ₱33.6M total · 0 flags

4. Implementation

Contract Amount

₱5,983,567.94

Progress

Reported complete (DPWH)

Start Date

January 18, 2018

Target End

July 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.