Construction of Drainage Structure22LB0234

Construction of Drainage System, Barangay Mandug, Davao City

Construction of Drainage System, Barangay Mandug, Davao City is a DPWH-tracked public work in DAVAO CITY (DAVAO DEL SUR), DAVAO DEL SUR, Region XI. Reported contract value: ₱5,445,000.00. Status: Reported complete (DPWH). Contractor on record: LLM UNIFIED BUILDERS & TRADING CORP FORMERLY:LLM CONCRETE PRODUCTS. Figures trace to sumbong.

DAVAO CITY (DAVAO DEL SUR), DAVAO DEL SUR, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bago Creek Flood Control Structure, Barangay Bago Gallera, Davao City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003151

₱1,573,469,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002814

₱56,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0008130

₱22,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0005935

₱15,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱5.4M total · 0 flags

4. Implementation

Contract Amount

₱5,445,000.00

Progress

Reported complete (DPWH)

Start Date

March 31, 2022

Target End

July 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.