Roads21K00065

CONST./IMPRVT OF ACCESS ROAD LEADING TO PROPOSED BUK AIRPORT(JCT. BUK-DAVAO CITY RD/CAMP 1, MARAMAG-

CONST./IMPRVT OF ACCESS ROAD LEADING TO PROPOSED BUK AIRPORT(JCT. BUK-DAVAO CITY RD/CAMP 1, MARAMAG- is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱132,728,777.88. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱132,728,777.88

Progress

Reported complete (DPWH)

Start Date

April 27, 2021

Target End

February 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.