Flood Control and Drainage25BH0303

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF SAN ANTONIO FLOOD CONTROL STRUCTURE SECTION 1, SAN AGUSTIN, ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF SAN ANTONIO FLOOD CONTROL STRUCTURE SECTION 1, SAN AGUSTIN, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱47,528,658.49. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: V B MANUBAY CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Antonio Flood Control Structure Sectiion 1, San Agustin, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,528,658.49

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

July 30, 2026

5. Audit