Bridges23BH0230

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR// STRATEGIC PUBLIC BULDINGS/FACILITIES -CONSTRUCTION OF GUCAB BRIDGE,BARANGAY GUCAB,ECHAGUE,ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR// STRATEGIC PUBLIC BULDINGS/FACILITIES -CONSTRUCTION OF GUCAB BRIDGE,BARANGAY GUCAB,ECHAGUE,ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱96,499,837.59. Status: Past target date (DPWH On-Going). Contractor on record: DALCON CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Santiago City, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

268 projects · ₱17.0B total · 43 flags

4. Implementation

Contract Amount

₱96,499,837.59

Progress

Past target date (DPWH On-Going)

Start Date

August 29, 2023

Target End

July 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.