Construction of Flood Mitigation Structure22EI0012

Construction of Bongabong River Control, Brgy. Luna Section, Sta. 0+000 - Sta. 0+334, Bongabong, Oriental Mindoro

Construction of Bongabong River Control, Brgy. Luna Section, Sta. 0+000 - Sta. 0+334, Bongabong, Oriental Mindoro is a DPWH-tracked public work in BONGABONG (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱48,999,950.04. Status: Reported complete (DPWH). Contractor on record: TWENTY SIXTEEN CONST AND GEN MERCHANDISE / LUMEL GLENN CONST. Figures trace to sumbong.

BONGABONG (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱14,291,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Hagan, Sta. 0+000 - Sta. 0+250, Bongabong, Oriental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002623

₱812,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003190

₱725,980,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-22-0005756

₱150,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002624

₱49,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003023

₱10,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱49.0M total · 0 flags

4. Implementation

Contract Amount

₱48,999,950.04

Progress

Reported complete (DPWH)

Start Date

April 13, 2022

Target End

January 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.