Construction of Flood Mitigation Structure24DM0092

Construction of Flood Control Structure at Brgy. Cabuyao, Padre Burgos, Quezon

Construction of Flood Control Structure at Brgy. Cabuyao, Padre Burgos, Quezon is a DPWH-tracked public work in PADRE BURGOS (QUEZON), QUEZON, Region IV-A. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ADAD ENGINEERING SERVICES & SUPPLY / LAICAN ENT INC. Figures trace to sumbong.

PADRE BURGOS (QUEZON), QUEZON, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Cabuyao, Padre Burgos, Quezon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008430

₱1,899,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004485

₱1,608,679.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0019787

₱85,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008431

₱175,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004487

₱115,778.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0005226

₱370,549.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱49.0M total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

April 11, 2024

Target End

December 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.