Buildings and Facilities19PC0072

CONSTRUCTION OF MPB (LNB BUILDING) PAYANAN, LUNA, APAYAO

CONSTRUCTION OF MPB (LNB BUILDING) PAYANAN, LUNA, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱2,938,544.53. Status: Reported complete (DPWH). Contractor on record: J G YACAS CONST SUPPLY AND EQUIPMENT RENTAL. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-19-0006576

₱44,912,000.00 · FY2019

Released to Apayao 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

110 projects · ₱1.7B total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER PACKAGE 4), LIBERTAD, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL ALONG ABULU

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTUR

Cagayan 2nd DEO, Region II

2025₱96.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL CONTROL STR

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF ABULUG RIVER REVETMENT 9 ALO

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER REVETMENT 5 AL

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
View all 110 projects →

4. Implementation

Contract Amount

₱2,938,544.53

Progress

Reported complete (DPWH)

Start Date

August 8, 2019

Target End

March 4, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.