Buildings and Facilities25CM0062

CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. RABANES, SAN MARCELINO, ZAMBALES

CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. RABANES, SAN MARCELINO, ZAMBALES is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱9,900,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MCB ZAMORA CONST. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Stabilization Structure along Gabor River, Phase 1, San Felipe, Zambales
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zambales 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 19, 2025

Target End

November 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.