GAA 2025 SSP25CI0033

BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SACOBIA RIVER (PHASE IV), MABALACAT CITY, PAMPANGA

BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SACOBIA RIVER (PHASE IV), MABALACAT CITY, PAMPANGA is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱148,479,108.14. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MCB ZAMORA CONST. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sacobia River at Mabalacat City, Pampanga (Phase 6)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Pampanga 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱148,479,108.14

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 7, 2025

Target End

November 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.