GAA 2024 DepEd BEFF24CN0202

CONSTRUCTION OF 2STY8CL, SUGUIT NHS, MARIA AURORA, AURORA

CONSTRUCTION OF 2STY8CL, SUGUIT NHS, MARIA AURORA, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱23,291,704.21. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: JAVEN CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay San Jose, Ma. Aurora, Aurora
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Aurora DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,291,704.21

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.