Roads15BK0095

CONSTRUCTION/CONCRETING OF ROADS BARANGAY AKLAN VILLAGE, DIFFUN, QUIRINO

CONSTRUCTION/CONCRETING OF ROADS BARANGAY AKLAN VILLAGE, DIFFUN, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱1,934,065.92. Status: Reported complete (DPWH). Contractor on record: KMD BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004539

₱560,000.00 · FY2016

Released to Southern Samar National Comprehensive High ScPS re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

289 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARITAO-QUIRINO ROAD, PACKAGE 1, QUIRINO

Region II, Region II

2023₱115.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - DIBUL - GAMIS ROAD CONNECTING FOSSILIZED FLOWER MAKING AND CORDON - AURORA ROAD (NATIONAL SECONDARY ROAD) IN SUPPORT OF

Quirino DEO, Region II

2023₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- DIVISORIA SUR-SAN SALVADOR-DUNGO ROAD CONNECTING BANANA CHIPS MAKINGFEEDS PROCESSING MUSCOVADO PROCESSING AND SUGAR CANE

Quirino DEO, Region II

2023₱28.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO EAGLE'S BEAK - BATUMBAKET, DIFFUN,QUIRINO

Quirino DEO, Region II

2023₱24.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION - ACCESS ROAD LEADING TO GOVERNOR'S RAPIDS, MADDELA, QUIRINO

Quirino DEO, Region II

2023₱19.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF LIWAYWAY-NRJ-RIZAL-A.BONIFACIO ROAD WITH EXCEPTION DIFFUN, QUIRINO

Quirino DEO, Region II

2020₱14.8M
Reported complete (DPWH)
View all 289 projects →

4. Implementation

Contract Amount

₱1,934,065.92

Progress

Reported complete (DPWH)

Start Date

March 17, 2016

Target End

April 22, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.