Roads23BK0022

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - DIBUL - GAMIS ROAD CONNECTING FOSSILIZED FLOWER MAKING AND CORDON - AURORA ROAD (NATIONAL SECONDARY ROAD) IN SUPPORT OF

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - DIBUL - GAMIS ROAD CONNECTING FOSSILIZED FLOWER MAKING AND CORDON - AURORA ROAD (NATIONAL SECONDARY ROAD) IN SUPPORT OF is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱29,397,031.66. Status: Reported complete (DPWH). Contractor on record: KMD BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

289 projects · ₱1.7B total · 0 flags

4. Implementation

Contract Amount

₱29,397,031.66

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

July 12, 2023