Roads21LF0127

CONCRETING OF NHJ TO BRGY. PALMA GIL FMR (PHASE II) BRGY. PALMA GIL, CARAGA, DAVAO ORIENTAL

CONCRETING OF NHJ TO BRGY. PALMA GIL FMR (PHASE II) BRGY. PALMA GIL, CARAGA, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 1st DEO, Region XI. Reported contract value: ₱11,938,109.92. Status: Reported complete (DPWH). Contractor on record: RITZ BUILDERS CONST INC FORMERLY:RITZTOK CONST AND SUPPLY. Figures trace to dpwh.

Davao Oriental 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Caraga Coastal Protection, Brgy. Central, Caraga, Davao Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao Oriental 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,938,109.92

Progress

Reported complete (DPWH)

Start Date

July 9, 2021

Target End

October 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.