Roads19J00049

CONSTRUCTION OF MISSING LINKS/NEW ROADS - LABANGAN - MIDSALIP ROAD, ZAMBOANGA DEL SUR

CONSTRUCTION OF MISSING LINKS/NEW ROADS - LABANGAN - MIDSALIP ROAD, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱48,734,306.27. Status: Reported complete (DPWH). Contractor on record: GENETIAN BUILDERS AND ENT INC FORMERLY: GENETIAN BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,734,306.27

Progress

Reported complete (DPWH)

Start Date

August 8, 2019

Target End

March 10, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.