Flood Control and Drainage20DL0017

B. ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS 1. FLOOD MANAGEMENT PROGRAM A. CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS 3. CONSTRUCTION OF FLOOD CONTROL ALONG PANDANAN RIVER, CALAUAG, QU

B. ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS 1. FLOOD MANAGEMENT PROGRAM A. CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS 3. CONSTRUCTION OF FLOOD CONTROL ALONG PANDANAN RIVER, CALAUAG, QU is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱9,534,299.78. Status: Reported complete (DPWH). Contractor on record: ARDA CONST AND SUPPLY. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Pandanan River, Calauag, Quezon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱322.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FIVE (5) STOREY AFP QUARTERS, BUILDING 1, LUCENA CITY, QUEZON, PHASE III

Region IV-A, Region IV-A

2024₱28.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 3. CONSTRUCTION OF ROAD, LALAGUNA - MONTECLARO - PISIPIS, LOPEZ

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 1. CONSTRUCTION OF LALAGUNA-CAWAYAN BARANGAY ROAD, LOPEZ, QUEZO

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 4. CONSTRUCTION OF STO. NIÑO IBABA - SUMALANG BARANGAY ROAD, LO

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 12. CONSTRUCTION OF CONCEPCION-KINALIN BARANGAY ROAD, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 11. CONSTRUCTION OF LALAGUNA - MONTECLARO - PISIPIS ROAD, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱19.8M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱9,534,299.78

Progress

Reported complete (DPWH)

Start Date

January 29, 2020

Target End

May 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.