Roads21DK0120

CONCRETING OF BRGY. ANOS FMR, BRGY. ANOS, TAYABAS CITY, QUEZON

CONCRETING OF BRGY. ANOS FMR, BRGY. ANOS, TAYABAS CITY, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱10,398,844.50. Status: Reported complete (DPWH). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

474 projects · ₱22.2B total · 0 flags

4. Implementation

Contract Amount

₱10,398,844.50

Progress

Reported complete (DPWH)

Start Date

May 3, 2021

Target End

July 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.