Roads20HK0039

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS-BAYAWAN-MABINAY ROAD K0148+1150-K0148+1800, NEGROS ORIENTAL

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS-BAYAWAN-MABINAY ROAD K0148+1150-K0148+1800, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱5,958,266.13. Status: Reported complete (DPWH). Contractor on record: H L J CONST. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Tinayunan River, Negros Oriental
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Negros Oriental 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱5,958,266.13

Progress

Reported complete (DPWH)

Start Date

January 31, 2020

Target End

May 20, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.