Buildings and Facilities24C00607

STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF THREE-STOREY DORMITORY BUILDING (PHASE 1)-CENTRAL LUZON STATE UNIVERSITY, PROVINCE OF NUEVA ECIJA

STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF THREE-STOREY DORMITORY BUILDING (PHASE 1)-CENTRAL LUZON STATE UNIVERSITY, PROVINCE OF NUEVA ECIJA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱19,896,517.43. Status: Past target date (DPWH On-Going). Contractor on record: TRISANT BUILDERS. Figures trace to dpwh.

Region III, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,896,517.43

Progress

Past target date (DPWH On-Going)

Start Date

November 18, 2024

Target End

June 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.