Buildings and Facilities24C00607

STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF THREE-STOREY DORMITORY BUILDING (PHASE 1)-CENTRAL LUZON STATE UNIVERSITY, PROVINCE OF NUEVA ECIJA

STATE UNIVERSITIES AND COLLEGES (SUCS)-CONSTRUCTION OF THREE-STOREY DORMITORY BUILDING (PHASE 1)-CENTRAL LUZON STATE UNIVERSITY, PROVINCE OF NUEVA ECIJA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱19,896,517.43. Status: Past target date (DPWH On-Going). Contractor on record: TRISANT BUILDERS. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,896,517.43

Progress

Past target date (DPWH On-Going)

Start Date

November 18, 2024

Target End

June 4, 2025

5. Audit